Richmond Bridge #29 Replacement Project

Posted Friday, December 20, 2024
News

This page contains updates from VTrans on the Richmond Bridge #29 Replacement Project
More information on this project can be found on the VTrans Project Page

https://vtrans.vermont.gov/projects/richmond-US2-bridge

RICHMOND BRIDGE BR#29
Replacement of Bridge no. 29 on US-2 in Richmond over I-89

​​​DATE:   December 19, 2024

TRAFFIC IMPACTS BELOW:
-None

PROJECT UPDATE:  Continued with the removal of the old U.S. Route 2 roadway on the west end of the project; Completed the installation of the final drainage structure.

CONSTRUCTION ACTIVITIES:​​​​​​
The project is shut down during the holiday season. Work will resume on January 6, 2025.
A SAFE AND HAPPY HOLIDAY SEASON TO ALL!

PROJECT TYPE: Complete bridge replacement

SPECIAL NOTICE: Please email sbarrett@coibsinc.com, reference Bridge#29, Richmond, if you would like to receive weekly project updates via email.

COMPLETION DATE: September 2025