OVERNIGHT CONSTRUCTION on Rt 2 STARTING SUNDAY, JUNE 11, 2023

Posted Friday, June 9, 2023
News

US-2 Rehabilitation Project
Richmond - Bolton US Route 2 Rehabilitation

https://vtrans.vermont.gov/projects/US2-richmond-bolton

​​​​​​​​​​​​​​REMINDER - OVERNIGHT CONSTRUCTION STARTING SUNDAY, JUNE 11, 2023

TRAFFIC IMPACT: Traffic Control with one-lane of alternating travel motorists can expect moderate traffic interruptions. Motorists can also expect to be traveling on a gravel surface between Snipe Ireland Road and Lemroy Court - PLEASE slow down and follow the posted speed limits.

​​​​​​​​​​​​​​CONSTRUCTION ACTIVITIES:
The following is the anticipated work schedule for the week beginning Sunday, June 11, 2023.

Sunday through Thursday - 7:00 p.m. to 7:00 a.m.:
​​​​​​​Grinding the existing roadway beginning at Lemroy Court and proceeding west through Richmond Village to the I-89 interchange
Lowering of the existing drainage structures

Monday through Friday - 7:00 a.m. to 6:30 p.m.:
Roadway maintenance throughout the gravel surface area.
General project clean-up work.